Location: | Tatlageac, Constanta |
Quantity: | 1200 ml |
Initial status: | Water infiltrations and leaks |
Executed works: | Epoxy mortar application, Cement insulating membrane application, epoxy resin injections |
Location: | Eforie Sud – Wastewater treatment plant |
Quantity: | 200 m |
Initial status: | Old concrete with cracks and coring |
Executed works: | Epoxy resin injections and wall plastering |
Location: | Satu Mare – Drinking water treatment plant |
Quantity: | 320 m |
Initial status: | Old concrete with cracks and coring |
Executed works: | Epoxy resin injections and wall plastering |
Observations: | The plant was in operation |
Location: | Sibiu – Drinking water treatment plant |
Quantity: | 500 m |
Initial status: | Old concrete with cracks and coring |
Executed works: | Epoxy resin injections and wall plastering |
Observations: | The plant was in operation |